Central Organisation for Railway Electrification (CORE) was set up in 1979 under the Ministry of Railways, at Allahabad. The responsibility entrusted was to carryout railway electrification over the entire network of Indian Railways. CORE units across the country are in the process of electrifying important Railway routes for harnessing maximum benefits from their traffic potential. As of now about 65.4% of freight and 51.2% of passenger traffic is hauled by electric traction on Indian Railways, and Cimechel is proud to have assisted CORE in marquee projects.

Sections Delivered for CORE

Timeline

  • Ongoing

    OHE and PSI on Group 213 of Western Railway

    Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, Single Phase, AC, Electrification OHE (High Rise OHE) & PSI Works" in 08 Nos of sidings in Samakhiyali - Gandhidham - Kandla Port-Adipur, Cross-over wiring of Jakhwada, Balance wiring of Sanand Yard, Balance wiring of Rajkot Yard and other sidings under Railway Electrification Ahmedabad unit

Commissioned Projects

  • 2023

    OHE and PSI on Group 212 of Western Railway

    Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, Single Phase, AC, Electrification Works including OHE & TSS as Composite Electrical Work" in Ahmedabad(Excl.)-Viramgam-Surendranagar-Rajkot (Incl.) section in Gr. 212 of Ahmedabad & Rajkot Divisions of Western Railway under RE Project Ahmedabad, Total 222.83 RKM/ 550.66 TKM

  • 2022

    OHE on Group 216 of South Eastern Railway

    Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, Single Phase, AC, Electrification including OHE & TSS Works" in Ranchi (Excl.) -Lohardaga -Tori (Excl.) section, Group - 216 in Ranchi Division of South Eastern Railway under RE Project Kolkata, Total 116 RKM/ 120 TKM.

  • 2021

    OHE and PSI on Group 193A of North Western Railway

    Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, Single Phase, AC, Electrification Works including OHE & TSS as Composite Electrical Work” in Hisar - Bhatinda-Suratgarh-STPS, Group - 193-A in Bikaner Division of North Western Railway under RE Project Ambala, Total 328 RKM/ 430 TKM.

  • 2019

    OHE and PSI on Group 170B of East Coast Railway

    Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, Single Phase, AC, Electrification Works including OHE & TSS as Composite Electrical Works in Titlagarh (Excl) - Dungripali (Excl.) section, Group-170-B in Sambalpur Division of East Coast Railway under RE Project Bhubaneswar, Total 106 RKM/ 230 TKMs

  • 2018

    OHE and PSI on Group 154 of Southern Railway

    Design, Supply, Erection, Testing and Commissioning of Traction Over Head Equipment at Harbour siding and SPIC Siding at Tuticorin in Madurai division of Southern Railway.

Come work with us!

We are looking to hire the best and the brightest minds to join our ever growing team.